ACP3
Air Campaign
Planning Process Panel |
- Shows Status of TIE 97-1 Demo in ACP Process Terms
- Uses Checkmate validated (realistic) terminology
- Uses 3 types of workflow status display:
- Graphical Display
- Colored COA Matrix - One column per COA
- Agents/To-do list with checkboxes
- Design is basis for later Process Control Panel
- Demonstration shows process status at:
- start of demo - COA-1 ready
- add COA-2
- add COA-3
- point where COA-2 has been created and is part way
through review; COA-3 is part way through being created;
sample associated displays available from this point
- point where COA-2 and COA-3 have been created, ACS Simulator has
run on both and other reviews are part way through
- COA-1, COA-2 and COA-3 are all developed (created and reviewed),
and a decision is awaited from the JFACC as to whether to brief the CJTF
- Start Demonstration
Based on O-P3 -
O-Plan Technology -
Funded by ARPI