co-ordinate mission requirements |
type |
UOB |
node |
23.1.35 |
idef0-ref |
12 |
objects |
Produces: EC Support Request
Produces: Target Msn Data
Produces: Target Msn SPINS
Produces: Unit Head's UP
Produces: refuelling requests
Uses: EC Planning
Uses: target planning updates
Uses: unit information
|
facts |
from 2 page Mitre diagram AOC Plans 1996
----------------------------------
from DRIY-TR-1994-001, Apdx D, Fig 1 |
constraints |
|
description |
There is an iterative loop on changes to mission data and what drives it in terms of support.
re Unit Head's up - this is the CAOC director's intention message which is sent out 48 hours before the ATO. It can be seen as a notional ATO. The unit representatives in the CAOC are involved in this process.
------------------------------------------
this process must start prior to 23.1.36 and 23.1.37 starting, and complete prior to them completing.
process starts: conflict start + 15 hours
process duration: up to 10 hours |